TOWN ROAD PAVING

The reconstruction of Witches Spring Road will start on Monday, August 6th. This project will take approximately
two an a half weeks to complete.

The schedule is as follows:
- August 6 - 14, All States Asphalt Inc. will be reclaiming the road, stabilizing the sub-base and fine grading. This process will be very disruptive to the flow of traffic.
- August 15 - 17, R & D Paving Inc. will be placing the base coarse of asphalt
- August 20 - 22, R & D Paving Inc. will be placing the wearing coarse of asphalt

This timeline may be adjusted because of weather.

PLEASE SEEK ALTERNATE ROUTES IF POSSIBLE
 

EXPECT DELAYS

Hollis DPW